IGS’ delivered projects and the market it served 1986-Present.

Exactly what is delivered, to whom and why the business holds a competitive advantage?

Major achievements, details of developments within the company which are essential to the success of the business. “IGS” – is now successfully in Business  from 1986 – Present time .

1986-1994, IGS acted as the General Contractor of Minneftegasstroy on construction of Uralsk gas complex facilities – (Contract No. 63-01 / 40001-108 (CSSR and USSR) Contract No. 63-09 / 30001-105 (GDR & USSR) Agreement between the government of USSR and CzechSSR, 16.12.1985) , – Agreement between the government of USSR and GDR (East Germany, 20.01.1986). During the 1986-1994 period, “IGS” was carrying out scopes of work to support the Program of the Intergovernmental Agreement between the former USSR and Czechoslovakia and between USSR and East Germany (GDR) to develop the Karachaganak Oil & Gas Condensate Field. “IGS” acted as a General Contractor with respect to the construction of industrial and civil facilities in Aksay and the Karachaganak Oil & Gas Condensate field. With the opening of a large oil and gas condensate field in Karachaganak, the Aksay town received an impetus for accelerated development. In the 1986 contractors from the Czechoslovak Socialist Republic and German Democratic Republic arrived to Aksay: Czechoslovakia and the GDR, took part in the construction of technological lines at the Karachaganak Oil & Gas Condensate Field and the town of Aksay. Many industrial enterprises were built. In the years between 1986-1994 a number of modern comfortable nine-storey residential buildings have been built with the integrated development of social infrastructure (schools, kindergartens, shopping and entertainment centers). Since the construction works in Aksay, micro districts are still referred to as - "Czech", "German" houses. Powerful urban sewage treatment facilities and drainage systems were constructed to go in line with the design developed by the USSRs Ministry of Oil and Gas. Aksay was developed and brought into line with the European quality overpass through the railway and the main urban roads. All these works were carried out by Contractors from Czechoslovakia and East Germany “IGS” was acting as the General Contractor.Client: USSR – Mingazprom (USSR’s Ministry of Oil and Gas). Project cost - $448,952,800.00.

1995  UNIT-2 at the Karachaganak Oil & Gas Condensate field- Gas pipeline branch to the village Zharsuat. Gas Distribution Auto station: Pipeline installation length 10.5 km, working pressure-50 kg-f / cm2. Three gas distribution stations: construction and instrumentation works. Client: General Management of Construction Committee of the Karachaganak Oil and Gas Condensate Field. Project Cost - $1,145,236.00.

1995-1997 - Aksai-Jambeyta gas pipeline 155 km long. The diameter of the pipe being 325 mm. The Client: JSC "Zakazstroygaz". Project cost - $8,881,499.00.

1996-1997 UNIT-3 facility at the Karachaganak Oil & Gas Condensate field. The construction of Gas Ventilating Compressor Building, Road repairs, pipe mechanical works, concrete works for the Pump building. Client: KOS (Karachaganak Organization Structure-BG & AGIP), General Contractor: BECHTEL. Project Cost - $1,064,681.00.

1996 UNIT-2 at the Karachaganak field. Gas pipeline to the wells. Overhaul repair of pipeline. Client: General Management of Construction Committee of the Karachaganak Oil and Gas Condensate Field. Project Cost $100,000

1996-1997 Construction of Pipelines Saztube-Elemes and Elemes-Oporniy - Client: "Kazakhturkmunai" JV, General Contractor Tekfen (Turkey. Project cost: $1,149,105.00.

1997-1998  Above ground facilities construction at Elemes-Oporny oil pipeline. Client: "Kazakhturkmunai" JV, General Contractor Fernas (Turkey) Project cost: $3,281,736.

1997-1998  Elemes-Saztube Oil field construction. Client: JV "Kazakhturkmunai" JV, General Contractor: Vegyepszer Co Ltd (Hungary). Project cost - $4,253,404

1998-2000  In 1998 Intergasstroy JSC created IGS-Sicim LLC–Joint Kazakh-Italian Company with Sicim (Italy) for the purpose of participating in the Karachaganak Development Project (Unit 2 and Unit 3) until Project completion. UNIT-3 at the Karachaganak field early works, Client: Karachaganak Petroleum Operating BV (KPO BV). General Contractor: IGS-Sicim LLC JV. Project cost - $6,749,472.00

1999  UNIT-3 Pipeline chemical cleaning. Work of Flowlines. Client: Karachaganak Petroleum Operating BV (KPO B.V.). General Contractor: IGS-Sicim LLC.JV .Project cost -$28,447.

1998-2000  UNIT-3 Wells construction. Collection satellite of early oil, gas and condensate. Client: Karachaganak Petroleum Operating BV (KPO BV); General Contractor: IGS-Sicim LLC JV. Project cost: $2,761,019.28.

1998 Reconstruction of the region hospital. Client: AGIP – British Gas. Project cost - $1,304,652.00.

1999 Arrangement of the Karachaganak field. Supply of road plates. Client: AGIP – British Gas. Project cost $100,000.

1999-2000  UNIT-2 Early works (earthwork, excavation, foundations installation). Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost: $5,055,199.74.  

1999-2000 UNIT-3 Interconnecting pipelines. Main construction earthwork, welded joints quality control works, insulation works. Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost: $1,918,712.23.

2000-2001 UNIT-2 Program of 2000 year. Client: Karachaganak Petroleum Operating BV (KPO BV); General Contractor: IGS-Sicim LLC.JV; Project cost: $8,193,737.56.

2000-2001 UNIT-3 Upgrade & Modernization. Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost: $3,179,066.00.

2000-2001 Atyrau pump station construction, reconstruction of the existing pumping station in Tengiz and the pipeline work within the framework of the Caspian Pipeline Consortium. Client: Caspian Pipeline Consortium, General Contractor Tekfen (Turkey); Project cost $8,506,430.00

2001 Lifting the water tank. The Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost: $340,000.00.

2002-2005 TCO (Tengizchevroil) Asset Development Projects Construction Camp, Contract № 571500-3-1029 for EPC and Commissioning in Tengiz (Construction of Shanyrak Village in Tengiz for Rotation Settlement (8,000-seat construction camp). Client: Parsons-Fluor-Daniel PFD International LLC; Project Cost $121,437,563.

2002 Reconstruction of the airport in Uralsk; Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost:  Project cost: $658,604.00.

2002-2003 Karachaganak Gas Condensate Field Development Project. Pumping station of technical water – painting, isolation work. Client: Karachaganak Petroleum Operating BV (KPO BV) General Contractor: IGS-Sicim LLC.JV; Project cost: $1,054,063.00.

2002-2004 In 2004 – The Joint Venture was dissolved; “IGS” acquired IGS-Sicim LLC and IGS-Sicim – becomes 100% Kazakh company. Atyrau Pump Station construction, reconstruction of existing Tengiz pump station and pipeline work within the framework of Caspian Pipeline Consortium. Client: Caspian Pipeline Consortium. Project Cost: $2 822 078

2001-2002 - Karachaganak Gas Condensate Field Development Project. UNIT-3. Clean gas pipeline from the Udoman River. Client: Karachaganak Petroleum Operating BV (KPO BV); Project cost : $1,203,868.00

1998 - 2011 In 1998,”IGS” formed a joint venture with the Italian company Sicim and became known as IGS-Sicim LLC JV (since 2011 -IGS-Corporation LLC instead of IGS-Sicim ) for the duration of the Karachaganak projects. The primary contracts (projects) delivered by the Joint Venture were the Unit-3 Priority Works, Upgrade of the Fire Water System, Metering System; Deluge System, Civil, Mechanical, and Electrical Works. Unit -2 Preliminary Civil Works, Site preparation, Year 2000 works, Civil Works, Under Ground Services; Interconnecting Pipeline 14 inch-Sweet gas/16 inch –Aksay water supply, Pipeline work total length 32 km; EPC of Sweet Gas Pipeline Project from Udoman River to Unit 3; Pipeline work total length 18 km; EPC of lifting of water tank; Unit 3 Integration works; Field integration Part 2-Year 2002 works; EPC of Industrial Water Pumping Station;Infiield Pipeline package “A”; Telemetry System for export Pipeline;EPC of Construction of Trunk Line TK -024;EPC of 24 inch Tie –in of Bolshoi Chagan Pumping Station to KTO Atyrau –Samara pipeline; Reconstruction of Uralsk airport;4th Stabilization & Sweetening Train – Piping Fabrication; 4th Stabilization & Sweetening Train – Pipe work &Equipment Erection ; Client: Karachaganak Petroleum Operating BV Amsterdam Holland ; Project Cost: $183,261,817.00.

2008-2011 Contracts on Karachaganak Projects, Train 4- Piping prefabrication works; Piping erection; Repairs rate; Pipe Supports; Equipment installation; Tanks erection;Client: Karachaganak Petroleum Operating BV Amsterdam Holland; Project Cost: $70,996,817.00.

2004-2010 The Kashagan Development Project: Plant Site Preparation & Piling; Plant Main works – Piping and Foundation works (as subcontractor of North Caspian Constructors); Utilities – Civil, Building and Equipment Installation (As subcontractor of BATEMAN); Utilities – Piping Project; As subcontractor of BATEMAN); Client: Agip Kazakhstan North Caspian Operating Company NV ; Project cost: $146,929,346.

2011 “IGS” group is made up of 2 companies: 1) IGS JSC – Head company & 2) IGS LLC its wholly owned subsidiary. The two companies are two legal entities

Intergasstroy JSC – which has Offices in Aksay, Fabrication Shops/Labs, (“IGS” has its own civil laboratory for testing concrete products for hardness, strength and compression), and facilities/equipment to provide any construction Project Support (logistic, accommodations, transportations).

IGS-Corporation - a wholly owned subsidiary, which was rebranded to  an Oil & Gas servicing Construction company.            

1) IGS JSC with a well equipped technological production base/yard (fabrication workshops) including a batching plant, open and closed areas for Loading/Unloading and storage of inert materials, heated storage facilities and railway branches (marshal railway connection), delivers a full range of civil, mechanical and installation works.

2) “IGS LLC” performs a full range of civil, mechanical and installation-works and holds the 1st category construction license.

If there is a necessity, both companies are able to work together mutually benefiting and bringing high value joint delivery execution - labor, equipment, human resources, etc.

2013-2015 Contract for Provision of Major Construction Works (Call off contract) №: AP/D/13/0111. Client: KPO b.v. (Karachaganak Petroleum Operating BV Amsterdam Holland); Project Cost: $81,480,712.50.

2014-2015 The Contract CW1191580 (K-200-001B-ON) on the FGP project in Tengiz - 3GI Site Preparation and Fencing. Client: TCO (TengizChevrOil). Project Cost: $16,111,537.47.   

2016 – 2017  Contract with “Weatherford Kazakhstan LLP”  for supply of Goods (crushed stone and other goods),power line constructing, Office construction in MS and Inspection Work Shop, Mobile office assembling, Asset Management. Client: Weatherford Kazakhstan LLP. Project Cost $2 070 604,5.

20182022 Contract with Schlumberger, KPO BV, Baker Hughes, Halliburton, Expro, Weatherford   – Call off Contracts –Fabrication shops/Labs, Logistics, Accommodations, Transportation. Types of services included leasing of production facilities, maintenance of workshops, supply of heat, electricity, water, cleaning and security services of objects Project Cost -  more than  $10 000 000 US Dollars

 IGS” has successfully executed works of over $1bn since 1986.

We are currently were invited  to participate in a tender for the provision of services for the maintenance of buildings, general construction and electrical works by the Client Karachaganak Petroleum Operating BV and to participate in a tender for the provision of services for the organization of a center for issuing personal respiratory protection equipment (PPE) and personal gas detectors (GS)Currently, we are participating in a number of tenders for the provision of construction services  and a number of services for the KPO Bv Client